NEWSLETTERS
In this Section...
Current Newsletter
Important Topics
Online Forms
Helpful Links and Information
Seminar Schedule
Past Issues ...
> Spring 2006
> Summer 2005
> Spring 2005
> Summer 2004
> Spring 2004
> Fall 2003
> Summer 2003
> Spring 2003
> Fall 2002
> Summer 2002
> Fall 2001
> Summer 2001
> Spring 2001
> Fall 2000
> Spring 2000
> Fall 1999
> Spring 1999
> Fall 1998
> Spring 1998

Past Issues - Summer 2002


Annual Legislative Report

This year's legislative sessions were among the most unproductive in a number of years. Certainly problems relating to reapportionment and tax reform contributed to the problem, to say nothing of the strained relationship between the House and the Senate. Special sessions were held for the budget, the education reorganization, and the reorganization of the duties of cabinet offices that were abolished. Despite this some issues relating to the construction industry were addressed. Since the process for transmitting bills passed by the legislature to the Governor and the time for the Governor to either sign or veto the bills is quite extended, there is a possibility that some of these bills may still be vetoed.

To Top


Alternative Permitting and Building Code

This bill allows a property owner to use a licensed engineer, architect or building code official to review plans and to make building code inspections. This bill also directed the Florida Building Code Commission to develop a rehabilitation code and directed adoption of the federal standard for economic hardship in meeting requirements for the Americans With Disability Act. This is a more relaxed standard from what had been required in Florida. The Commission was also directed to establish an informal process for rendering non-binding interpretations of the Building Code. Criteria for adoption of local amendments to the Code were added. This will make it more difficult for local entities to amend the Code. This bill will become effective upon becoming law (subject to the Governor's veto).

To Top


Workers Compensation

There was considerable discussion of workers compensation issues, but not much was accomplished. In the ongoing struggle over exemptions from requirements for workers compensation, a further step was made towards elimination. For commercial construction jobs in excess of $250,000.00, exemptions from workers compensation coverage will no longer be permitted. This bill also imposed additional record keeping requirements on those claiming an exemption. In addition, if the records are not produced within three business days, a stop work order may be issued.

Upon determination that a person has failed to secure workers compensation coverage as required by law, a stop work order within 72 hours of making the determination is now required. A penalty in the amount of the premium evaded or up to twice the amount of the premium evaded or $1,000.00, whichever is greater, is now required for failure to secure coverage. The bill also made changes designed to expedite the dispute resolution process in the hopes that this will reduce costs for the overall administration of the workers compensation system. It also authorized rewards of up to $25,000.00 to persons providing information leading to the arrest and conviction of anyone committing insurance fraud. In addition, employers are now required to post a notice informing employees of the anti-fraud reward program.

To Top


Drug Free Workplaces

This bill requires a drug free workplace program for contractors who do work on public projects. Drug testing of employees and job applicants is required to qualify as a drug free workplace. This bill will take effect October 1, 2002 (subject to veto).

To Top


Sales Tax Amendment

This is a proposed amendment to the State Constitution to create a commission of six legislators each from the House and the Senate to review sales tax exemptions. The Commission will be able to eliminate any exemption by a vote of seven members. The Legislature can restore the exemptions within two legislative sessions. Construction services will be one of the items that currently has an exemption which will be subject to review.

To Top


State Procurement

This bill impacts purchases from the State, including construction services. Notice of procurement decisions will be posted on a website maintained by the Department of Management Services. The 72 hour time limit for filing a Notice of Protest commences upon the posting. The amount of the bond a protester must file is now one (1%) percent. Previously it was the lesser of $5,000 or one (1%) percent of the contract price submitted by the protester. If not vetoed by the Governor, these provisions will take effect July 1, 2002.

To Top


Underground Facility Damage

The one-call access notification center may receive notices by e-mail and fax in addition to the toll free telephone number. It requires excavators to pre-mark the excavation site under certain circumstances and requires hand digging and similar procedures in a tolerance zone. The effective date is October 1, 2002. If you would like copies of these bills or are in need of further explanation, please do not hesitate to contact us.

To Top


Arbitration May Now Be Optional

Over the years there has been disagreement over the validity of an arbitration clause which permits one side but not the other to decide if a dispute will be arbitrated or litigated. The argument for its invalidity has been that there is a lack of a mutual obligation to arbitrate. A recent Florida case appears to have resolved that question. In Avid Engineering, Inc. v. Orlando Marketplace, Ltd., the engineering company objected to arbitration on the grounds that the contract gave the other party discretion to decide whether to arbitrate without giving the engineer the same right.

The Court reasoned that the engineer agreed to perform services in exchange for payment. This was deemed sufficient consideration to bind both parties to all obligations under the contract, including the optional arbitration clause and that the arbitration provision was not void for lack of mutuality of obligation. The Court pointed out that the optional arbitration clause had not required the engineer to give up any claims or damages that it could have received in Court. The contract was merely substituting a forum for deciding those claims or damages.

To Top


Acceleration

Acceleration of a contractor's performance may arise in two situations. The first occurs when a specific order is issued under the express contract to complete the project prior to the originally scheduled completion date. The second theory of acceleration is based on the effects of excusable delay on the contractor's time of performance. When a contractor encounters excusable delay in completing a contract, the contractor is entitled to a timely extension of the contract time in which to complete the work. When the owner or its representative refuses the extension or simply does not respond, a constructive acceleration of the contract exists since the contractor effectively has less time than originally promised in which to perform the required work.

Some contracts specifically allow the owner to accelerate the time of performance of the work. Generally, when the contractor is directed to complete the work in advance of the scheduled completion date, and the order is signed by the owner or his representative, it is clearly an ordered change and the contractor's claim for additional compensation should be presented in accordance with the standard change order procedures. A more complex situation arises when the contractor encounters an excusable delay and requests an extension of the contract time but the owner refuses to recognize the delay and requires that the contract be completed by the originally specified date.

Or, in another situation, the owner may recognize a delay but of a shorter duration than that to which the contractor is entitled. In these circumstances the contractor is placed in the position of either risking contract default if it finishes at a time later than that required by the owner or expending extra funds in order to overcome the excusable delay and finish the contract as demanded. Although the owner may not have issued any express order under the changes clause which would qualify as ordered acceleration, many courts have developed the doctrine of constructive acceleration to encompass those situations where the owner acts in such a way that it will be deemed to have ordered acceleration.

Courts generally look to the following factors when analyzing a claim for constructive acceleration:

a. The contractor has encountered excusable delay for which it is entitled to a time extension;

b. The contractor specifically requested a time extension from the owner according to the contract provisions;

c. The owner failed or refused to grant the extension;

d. The owner either: (i) ordered completion within the original performance period, or (ii) acted in such a way that it was clear that the owner still required the contractor to complete within the original performance period;

e. The contractor gave notice to the owner that it considered the actions of the owner a constructive change order for acceleration; and

f. The contractor actually incurred excess costs as a result.

When faced with a possible acceleration situation, the contractor should make all reasonable attempts to complete the project on schedule and carefully document all impact costs resulting from the acceleration. Failure to complete the project on time exposes the contractor to potential claims by the owner for liquidated damages, lost rents, lost profits, and extra financing costs, and may weaken the contractor's claim for acceleration damages.

To Top


Incorporation By Reference Clauses in a Contract

The purpose of this type of contract provision is to bring another document into the contract without fully setting forth the incorporated document. It may place "hidden" obligations in your contract. These clauses are enforced by the Florida courts. Most often we see the Plans and Specifications incorporated into the contract. The effect is to make them a part of the contract documents. The obligation to fulfill the provisions of the Plans and Specifications is just as binding as any contract clause actually written in the contract. This can extend down several levels. In our example the Plans and Specs are now part of the contract. The Specifications may then incorporate other documents such as installation requirements. The effect of this is to incorporate those requirements into the contract. The fact that these requirements were not included in your estimate will not prevent enforcement of these obligations.

Another typical incorporation is found in subcontract agreements where the contract between the owner and contractor is incorporated by reference. Again all of the terms of that general contract are now terms of the subcontract including the documents incorporated into the general contract. The subcontractor then assumes an obligation to perform under those terms. The fact that you have not seen the incorporated documents will not relieve you of their requirements.

Since these types of clauses are enforceable, a failure to comply is a breach of contract subjecting you to damages for any failure to comply. The first step, of course, is to obtain each of these documents, before you sign a contract. All of the incorporated documents must be reviewed in detail to determine the extent of your obligations. Any provisions that are not acceptable should be specifically deleted from your contract.

Contracts are like seat belts. Putting them on takes time and energy and on most trips they serve no useful purpose. However when an accident happens they become your most important accessory. Many jobs get done without ever looking at the contract. However, when problems arise on the job the first thing that comes out of the file cabinet is the contract. You may be in for some unpleasant surprises if you haven't looked at the incorporated documents.

If you need additional information, please contact our office and we will be happy to assist you.

To Top

 
Site design and hosting by: