NEWSLETTERS
In this Section...
Current Newsletter
Important Topics
Online Forms
Helpful Links and Information
Seminar Schedule
Past Issues ...
> Spring 2006
> Summer 2005
> Spring 2005
> Summer 2004
> Spring 2004
> Fall 2003
> Summer 2003
> Spring 2003
> Fall 2002
> Summer 2002
> Fall 2001
> Summer 2001
> Spring 2001
> Fall 2000
> Spring 2000
> Fall 1999
> Spring 1999
> Fall 1998
> Spring 1998

Past Issues - Fall 1999


Annual Legislative Update

We are pleased to bring you our 1999 Legislative Update. Every year the Florida Legislature tinkers with some of the statutes that govern the construction industry. While this is always a concern, we seemed to have done reasonably well this year. There are the usual changes in the Lien law as well as changes to the licensing laws. The big news is the Miorelli "fix." As this legislation progressed it did not appear to be of much help. However, during the legislative process there were significant changes so that in the final analysis it looks to be an improvement.

To Top


Miorelli Fix

House Bill 311 is a codification and an improvement on the recent decision by the Florida Supreme Court in County of Brevard v. Miorelli Engineering, Inc., 703 So. 2d 1049 (Fla. 1997). The court held that a public body was subject to the implied covenants of good faith and fair dealing that exist in every contract, but it had no obligation to pay for any extra work for which a change order was not executed.

This bill codifies the obligation of good faith and fair dealing arising from the breach of an express provision or an implied covenant of a written agreement or a written directive issued by the public authority pursuant to the written agreement. It further provides that the public authority and the contractor have all of the same rights and obligations as a private party under a similar contract, with the exception that any attempted oral modification of either the written contract or written directive will not be binding.

For those working on public projects, this means that a written directive to perform extra work should be sufficient to allow you to recover for that work. Note that this section applies only to contracts entered into on or after July 1, 1999. Consequently, it has no impact on any current contract disputes or existing projects.

To Top


Licensing Changes

Senate Bill 2268 directs the Construction Industry Licensing Board and the Electrical Contractors Licensing Board to establish a job scope for each license category. The purpose is to establish uniformity of job scopes between the state and local jurisdictions. It also provides a procedure for converting from a registered contractor to a certified contractor. This requires application to the CILB or the EILB and meeting the following requirements:

1. A valid registered license in one of the categories for which the CILB or EILB issue licenses.

2. Passage of a written examination substantially similar to the examination required to be licensed as a certified contractor.

3. Five years experience as a contractor in the category to be licensed. Only time periods when the license is active and the contractor is not on probation will count.

4. No revocation of the license at any time or suspension within the past five years, or assessed a fine in excess of $500.00 within the past five years.

5. Meet the requirements for insurance and financial responsibility under the state statute.

This Bill also directs that a study be conducted to determine the fiscal impact on local governments of instituting a single tier regulatory system for construction, electrical and alarm system contractors. It contemplates that the system would be established by prohibiting, as of a certain date, issuance of any new local licenses in any categories licensed by the state. This report must be submitted to the Legislature by December 1, 1999.

This is clearly intended to set the stage for a single tier licensing system. It provides that existing locally licensed construction, electrical and alarm subcontractors will have the option of continuing and concluding their careers as locally licensed registered contractors.

It should not be assumed that the Legislature will necessarily either adopt a single tier regulatory system or follow the pattern set out in this Bill.

This Bill also adds some help in avoiding paying for more than one occupational license. By statute, once a business has paid an occupational license tax for the current year, it cannot be required to pay it in any other jurisdiction. This statute has not always been followed by local jurisdictions. This statute now allows any contractor who is required to pay an additional tax, standing to sue and recover attorneys' fees.

This Bill also provides that a contractor does not commit a disciplinary violation when relying on a building code interpretation rendered by a building official or someone authorized to enforce the building code in the absence of fraud or deceit by the contractor or gross negligence by the building official.

To Top


Construction Liens and Bonds

Section 255.05 relating to bonds on public projects has been amended to provide for services of any notices in accordance with section 713.18. That section generally provides for three methods of service:

1. Actual delivery.

2. Certified Mail with a return receipt.

3. Posting on the property.

In addition section 713.18 was amended to allow service by overnight or second day mail. In any event, it is clear that all bond notices should now be sent by one of these methods. We continue to recommend the use of Certified Mail with a return receipt as the best of these methods.

Many of the amendments contained in this Bill relate to the timing of the service of Notice of Nonpayment or recording of a Claim of Lien. Some case law has suggested that the 90-day period for each of these may not begin until a Certificate of Substantial Completion or a Certificate of Occupancy has been issued. This Bill eliminates use of those milestones for determining the time for service or recording. It now requires that any service of Notice of Nonpayment or recording of a Claim of Lien must be within 90 days from the last day of furnishing labor, services or material by the claimant.

Section 713.06 provides for service of a Notice to Owner. That section provided that the notice had to be substantially in the form provided in the statute. In some cases it was held that a failure to use the form in the statute meant that the Notice to Owner was not proper. This resulted in the loss of all lien rights. The statute now provides that the notice "may" be in substantially the form provided by the statute, but it must include the information in the warnings contained in the statutory form. Presumably this means that some variation in the middle part of the Notice to Owner would be tolerated. It is our recommendation that you continue to use the statutory form to avoid any difficulties.

This Bill now specifically provides that the form of the Notice to Contractor under section 713.23 or section 255.05 may be combined with the Notice to Owner. This is a practice that has been going on for many years and we are not aware of any problems as a result. However, this should resolve any issue in the future. See our website for a copy of this form.

Section 713.13 sets out a statutory form for Notice of Commencement without an absolute requirement that the form be used. This Bill amends the statute to specifically identify the items that must be contained within the Notice of Commencement. These are as follows:

1. The name and address of the owner.

2. The name and address of the contractor.

3. The location or address of the property being improved.

The authority issuing the building permit is now required to verify that these items in the Notice of Commencement are consistent with the information contained in the building permit application.

An exemption to the requirement for a Notice of Commencement was created for a direct contract to repair or replace an existing heating or air-conditioning system for less than $5,000.00.

Section 713.16 allows for a demand for copies of contracts and other information. This Bill amends that to specify exactly what information is required. It further goes on to change existing law so that the failure to furnish the statement under oath does not invalidate the lien. This particular amendment is deemed remedial in nature. This means that it becomes effective immediately upon becoming law and will apply retroactively to May 4, 1994.

A provision has been added to section 713.23 making it clear that a Waiver and Release of Lien also constitutes a waiver and release of the right to make a claim against a payment bond under section 713.23.

To Top


Venue

Venue is the place where a lawsuit to enforce a contract may be brought. Venue is usually in the county where the defendant resides or where the case arose (generally the location of the project).

However, the parties to a contract have the ability to specify in their contract another venue for any litigation. This has occasionally resulted in out of state contractors requiring venue where their home office is located rather than in Florida.

The law in Florida has been that where the parties agree to venue, then it is enforceable. House Bill 681 outlaws this practice. Suit must be filed either where the defendant resides or where the property is located. This only applies to venue outside of Florida. For example, a contractor located in Tampa could still agree to venue being in Miami.

If you need additional information, please contact our office and we will be happy to assist you.

To Top

 
Site design and hosting by: