NEWSLETTERS
In this Section...
Current Newsletter
Important Topics
Online Forms
Helpful Links and Information
Seminar Schedule
Past Issues ...
> Spring 2006
> Summer 2005
> Spring 2005
> Summer 2004
> Spring 2004
> Fall 2003
> Summer 2003
> Spring 2003
> Fall 2002
> Summer 2002
> Fall 2001
> Summer 2001
> Spring 2001
> Fall 2000
> Spring 2000
> Fall 1999
> Spring 1999
> Fall 1998
> Spring 1998

Past Issues - Fall 2002


Contracting with Lessees

Contractors performing work for lessees face special problems in enforcing construction lien rights. Normally the right to a construction lien extends only to the title and interest of the party who contracts for the improvement. However, when an improvement is made by a lessee in accordance with a lease agreement, the lien extends to the interest of the lessor.

Where the lease expressly provides that the interest of the lessor will not be subject to liens for improvements and the lease or a short form thereof is recorded in the public records a Claim of Lien will not be valid as to the interest of the lessor. Consequently, contractors need to look closely at the financial ability of the lessee before entering into a construction contract since only the leasehold interest would be lienable.

To Top


Notice of Contest Lien

Florida Statutes ' 713.22 provides a method for shortening the statute of limitations for a construction lien. An owner may shorten the normal one-year statute of limitations of a construction lien by recording a Notice of Contest of Lien with the clerk of court in the county where the lien is recorded.

When a Notice of Contest is recorded, the clerk's office will mail a copy to the lienor informing him that any suit to enforce the lien must be started within 60 days of serving the notice. Any lien which is not sued upon within this 60-day time period will be extinguished automatically.

When the party contracting directly with the governmental entity (usually the general contractor) receives payment, it is required to make payment to its subcontractors and suppliers within fifteen (15) days after receipt of payment. The subcontractor, in turn, is required to make payment to its subcontractors and suppliers within fifteen (15) days after its receipt of payment.

Not only will an untimely response render the lien invalid, the lienor may be responsible for the owner's attorney's fees to the extent the claim must be defended in court. Once a lien has been recorded, you should analyze any and all documents received from the clerk of court or the owner to ensure that your lien rights are preserved.

Notice of Contest is applicable to claims against bonds as well.

To Top


Cases of Interest to Conractors - No Change Order Required

An appellate case has addressed some issues arising out of the Miorelli decision by the Florida Supreme Court. Miorelli held that a contractor, when working for a public body, could not receive payment for changes in the work unless there was a written change order. In Town of Palm Beach, v. Ryan Incorporated Eastern, 786 So. 2d 665 ( Fla. 4th DCA 2001) the parties entered into a contract for construction of sewers and pipes according to the plans and specifications provided by the city.

During the course of the work Palm Beach failed to provide electricity for the dewatering pumps as promised and refused to allow operation of the diesel-powered pumps after 4:00PM. There were also problems with the plans. A section of piping had much greater curvature than what was shown on the plans. When the pipes were tested they failed. Investigation showed that the pipes had moved due to inadequate dewatering. The Contractor performed the repairs without obtaining a change order.

Palm Beach refused to pay for the repairs or additional work related to the curved pipe based on the Miorelli requirement for a written change order. Ruling in favor of the Contractor, the Court pointed out that even a public body has a duty not to hinder, obstruct or unreasonably delay the performance of the work by a contractor and that the repair work was necessary to bring the project into conformity with the contract. This meant that the repairs were not outside the original scope of the work so a change order was unnecessary.

To Top


Cases of Interest to Conractors - Be Careful About Puffing

In The Gables, Gables/Kovens, Inc. and Gables Design Group, Inc. v. Arthur B. Choate, 792 So. 2d 520 (Fla. 3rd DCA 2001) a developer and interior design firm learned that a court will not protect you after entering into a bad contract. The Owner signed a purchase agreement with the Developer for a $700,000 luxury condominium to be completed by May 1, 1996. In December of 1996 the unit was still incomplete. At closing, an interior finish contract was incorporated into the closing agreement providing that if the unit was not finished within 30 days Gables would pay Choate $5,000 per week.

Construction continued for another six months until finally Gables abandoned the project and refused to pay the $5,000 per week delay damages. Florida law recognizes that where damages are not clearly ascertainable, parties to a contract may agree to a predetermined amount of damages that will flow from a breach of the contract. However, where actual damages for breach of agreement are readily ascertainable and sum agreed to be paid in event of breach is disproportionate, the sum will be regarded as a penalty and void.

The court decided in favor of Choate reasoning that the actual amount of damages could not have been determined at the time of closing and therefore the $5,000 per week pre-determined damages provision should be enforced. This case also shows how long it can take to get a case finished.

To Top


If you need additional information on any of these bills, please contact our office and we will be happy to assist you.

To Top

 
Site design and hosting by:
align="left" valign="top" background="marlowe_firm_images/spacer_green.gif">
Site design and hosting by: